When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

Rename the number. 18 thousands=
After 30 baseball games, A Rod had 25 hits . If after 100 games he had 80 hits, what is the average hits per baseball game.
Is it possible that there are even prime numbers gearter than 100
Is 0.3333 a rational number and why
Which groups listed on and he map probably changed the least over time since crossing the Bering land bridge
What is 31/100, 51/100, 67/100, 89/100, 97/100, and 50/100 simplified..? Please answer..
Georgia. 0.029 can be written as 29 / 100 is he correct
A keg cost $65 plus a $15 refundable deposit. You deliver two ( 2 ) kegs and pick up three ( 3 ) empty kegs, what would the total cost be?
Why did scholars have problems recognizing the traditions of native American literature
an apple orchard sells apples in bags of 10 the orchid sold a total of 2430 apples one day how many bags of apples was this