contestada

thirty-six men can paint a shopping mall in 25 days. How many days will it take 15 men to paint the mall, if they work at a same rate?​

Respuesta :

ksperu ksperu
  • 04-05-2021

Answer:

12.5 days

Step-by-step explanation:

Given

No of workers= 30

Time taken to paint shopping mall= 25 days

Assume time taken for 15 men =X

Time taken for 15men to paint X= (15*25)/30

=12.5 days

Answer Link

Otras preguntas

Who were the first 3 American presidents in order?​
The formula S=√SA/6 gives the length of the side, s, of a cube with a surface area, SA. How much longer is the side of a cube with a surface area of 180 square
Inez spent $15.75 on 7 bandanas. About how much did each bandana cost? Round to the nearest cent. Each bandana costs $​
Find the area of this polygon. Enter your answer in square units.
please answer this question​
100 POINTS AND BRAINLEIST TO WHOEVER ANSWERS Do you think a chemical reaction took place in Part 1 when you added the galvanized nail to the acid and water, and
A group of LANs connected together forms a: A. POP B. WAN C. MAC D. IP
What is the difference between a fief and a manor?
why is it important to engage communities in preparedness efforts
ANSWER ASAP PLEASE!Why are macromolecules also known as polymers?