A piece of work takes 20 labourers to complete in 10 days. how many labourers will complete the same job in 25 days if they work at the same rate?​

Respuesta :

denimjackets23
denimjackets23 denimjackets23
  • 04-09-2021

Step-by-step explanation:

If 20 labourers=10 days

x labourers = 25 days

10x= 25×20

[tex] \frac{10x}{10} = \frac{25 \times 20}{10}[/tex]

Cancelling out by 10 on both sides

[tex]x = \frac{25 \times 2}{1} \\ x = 50 [/tex]

Therefore, it takes 50 labourers to complete the work at the same rate in 25 days.

Answer Link

Otras preguntas

If the solution surrounding a cell contains the same amount of solute as the cytoplasm the osmotic condition is said to be:
Which measure of central tendency​ (the mean or the​ median) best describes the surface roughness of the sampled pipe​ sections?
Identify and explain three major issues that cut across psychology
What is equivalent to the quotient of 10 plus x and y minus 3
Cell membranes are structured so that molecules can pass in and out if the cell across them. While both plant and animal cells have membranes, plant cells also
How did glacial movement affect the Nordic countries? Select all that apply. A. caused the formation of fjords B. caused the North Atlantic Current C.
LN bisects KLM into two congruent angles measuring (3x-4) and (4x-27). Find klm
Irrigation improves the yield of strawberries per acre according to the function S=-(w-2)^2 +50 where S is the number of pints of strawberries grown per acre an
Person who is unable to make vocal sounds is said to have bradyphasia.question 5 options:truefalse
Can someone please answer that for me