8 men complete a work in 40 days. How many days will be taken to complete the samed work if 2 more men join them.

Respuesta :

rpband00
rpband00 rpband00
  • 04-04-2018
Hello there,

There were 8 men who completed a task in 40 days. If you divide 40/8 that is 5 so it took them 5 weeks to complete this task.

Now if you add two more men, that makes it 10 men to complete the work in 50 days. If you divide 50/10 that is 5.
10 days

Hope this helped!

Answer Link

Otras preguntas

A scale drawing is 21 inches long and 9 inches tall the real item is 30 feet tall how long is it
the greatest diversity of plants and animals is found in this biome.
the pink dress has too many pockets. what is the adjective
what type of force does a backpack exert on the bodys back and hips
Put a Sentence for reputation
Children go through many different types of changes as they develop. a. True b. False
This ballot has such an enormous amount of information on it that it might be difficult to understand
Compare the decimals 9,135.40 and 9,135.4.
what is the product of -0.2 and -6.8
How can I answer this question?